Description of the Works

The erection of the second tower crane for the CAP site will take place on Thursday 18th June. The 120 tonne mobile crane will arrive at 7am and the escort vehicle will take it to the site. Several articulated lorries will travel from Holywell car park to the site during the day to erect the crane. All works should be completed by 6pm on Thursday. Whilst the articulated lorries are driving through site there may be traffic delays along university road this will only be temporary and traffic should run normally most of the day.

Timescale

Wednesday  18th June 7-am to 6-pm